On March 7, 2023, the functional test (cold run test) of the STEMA® JU 15 stamping machine was carried out with the TŘINECKÉ ŽELEZÁRNY team from the Czech Republic in our works!

Under the project management of Dr.-Ing. Benjamin Berger, all tests and work simulations were successfully completed as expected. The STEMA® JU15 will be delivered to the customer TŘINECKÉ ŽELEZÁRNY in the shortest possible time!

We thank our customer, TŘINECKÉ ŽELEZÁRNY, for the trust and good cooperation and look forward to the installation and commissioning in April 2023 in the Czech Republic.

See you in Trinec!