The successful commissioning of the new STEMA JU10 in voestalpine Schienen GmbH was finished.
Today our managing director, Mr. Bruno Berger, signed an order for delivery and commissioning of a stamping machine JU20 for Panzhihua New Steel & Vanadium Company LTD.
Customer: PANGANG GROUP INTERNATIONAL ECONOMIC & TRADING CO.,LTD
Supplier: UTEC Engineering GmbH
Delivery date: May 2008
The Rail Stamping Machine type JU10 was tested and accepted from Mr. Schmid and his team voestalpine Schienen GmbH!
The commissioning takes place from August 27th to September 03rd, 2007 .
Today our managing director, Mr. Bruno Berger, signed an order for the delivery and commissioning of a stamping machine JU10 for Duisburg.
customer: TSTG Schienen Technik
supplier: UTEC Engineering GmbH
delivery date: April 2007
Today our managing director, Mr. Bruno Berger, signed an order for the delivery and commissioning of a stamping machine JU10 for Donawitz.
Auftraggeber: Voestalpine Schienen GmbH
Auftragnehmer: UTEC Engineering GmbH
Lieferung: Juni 2007
The commissioning of the stamp machine JU20 began on the 28. March 2006. After two-part fine adjustment of the stamp machine the commissioning completed succesfully on 1. May 2006.
Start of commissioning:
Adjustment: 29. April 2006
Turnover of the stamp machine: 1. May 2006
Contract signature: 1. May 2006
Length of commissioning: 3 days
Today our managing director, Mr. Bruno Berger, signed an order for the delivery and commissioning of a stamping machine JU15 to Turkey.
Customer: Karabük Iron & Steel Works A.S
Contractor: SMS Meer GmbH
Supplier: UTEC Engineering GmbH
Delivery date: May 30, 2006
Successful commissioning of the new Rail Stamping Machine JU20 in the rail rolling mill Pangang was finished on Mai 15, 2005.
The rail stamping machine is able to stamp rails with a speed of max 5 m/s.
Customer: Panzhihua Iron & Steel Company
Generall contraktor: SMS Meer GmbH
Supplier: UTEC Engineering GmbH